What is a "change order" in construction contracts?

Study for the California Pipeline Contractor (C-34 License) Exam. Prepare with multiple choice questions, flashcards, hints and detailed explanations. Pass your licensing exam confidently!

Multiple Choice

What is a "change order" in construction contracts?

Explanation:
A change order is a formal written modification to a construction contract that changes the scope, price, or schedule, and it must be agreed to by both the owner and the contractor. It records precisely what work is added, removed, or altered, the cost impact, and any change to the completion date, and it becomes part of the contract documents. Change orders are used when site conditions or client requests require adjustments beyond what was originally agreed, ensuring there is a clear, traceable record of approved changes. Verbal instructions to modify work aren’t considered change orders, and a stop-work directive is a separate action, not a contract change. If a change affects scope, cost, or timing, it should be captured in a written change order.

A change order is a formal written modification to a construction contract that changes the scope, price, or schedule, and it must be agreed to by both the owner and the contractor. It records precisely what work is added, removed, or altered, the cost impact, and any change to the completion date, and it becomes part of the contract documents. Change orders are used when site conditions or client requests require adjustments beyond what was originally agreed, ensuring there is a clear, traceable record of approved changes. Verbal instructions to modify work aren’t considered change orders, and a stop-work directive is a separate action, not a contract change. If a change affects scope, cost, or timing, it should be captured in a written change order.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy